North Central Railway

Prayagraj Division · IRPSM Work Intelligence

6
DR

Sanctioned Work Position

North Central Railway

Prayagraj Division

1281

Projects

₹32,14,18,495

Total Original Cost

₹33,00,41,340

Total Last Sanc Cost

₹77,52,484

Total Expenditure CFY

₹2,86,98,836

Total Outlay Modified for CFY

42.08%

Financial Progress %

45.04%

PH Physical %

53.10

Physical Progress Weighted

Remarks

Filters

Slicers apply to every tile, chart and table on this page

District wise projects count

Count of PROJECTID by Project Status

Total Budget by Plan Head

Total Expenditure by Year of Sanction

Physical perc and Financial Progress % by Station

Detailed table — ALLOCATION WISE

2075 allocation rows from sheet 2.AllocationWise · amounts as imported (₹ in thousands)

Plan HeadName of WorkPB itemYear of sanctionAllocationOriginal costLast sanc costExpenditure
11Etawah-Mainpuri (57.5 km)PB/21997-1998CAP₹12,00,000₹31,26,500₹34,72,188
11Etawah-Mainpuri (57.5 km)PB/21997-1998EBRS₹25,000₹100₹0
11Etawah-Mainpuri (57.5 km)PB/21997-1998SF₹2,00,000₹3,000₹2,873
15Allahabad Division - Construction of Kanpur Fly-overPB/362017-2018CAP₹1,78,97,300₹0₹13,203
15Allahabad Division - Construction of Kanpur Fly-overPB/362017-2018EBRIF₹10,000₹0₹0
15Pankidhan-GMC (2 km) 4th line (PB#72/NR/2022-23)PB/402022-2023CAP₹1,78,500₹1,78,500₹50,672
15Aligarh-Ghaziabad - 3rd line (106.15)PB/182003-2004CAP₹3,14,327₹49,92,820₹44,89,170
15Aligarh-Ghaziabad - 3rd line (106.15)PB/182003-2004CF₹34,619₹1₹5,730
15Aligarh-Ghaziabad - 3rd line (106.15)PB/182003-2004DEPRVN₹39,60,081₹1₹0
15Aligarh-Ghaziabad - 3rd line (106.15)PB/182003-2004DPO1₹0₹1₹0
15Aligarh-Ghaziabad - 3rd line (106.15)PB/182003-2004EBRIF₹0₹72,680₹72,680
15Panki-Bhaupur - 3rd line (11.38 km)PB/192005-2006CAP₹2,36,900₹5,16,697₹5,75,838
15Panki-Bhaupur - 3rd line (11.38 km)PB/192005-2006CBOND₹0₹0₹70,000
15Panki-Bhaupur - 3rd line (11.38 km)PB/192005-2006DPO1₹0₹0₹20,000
15Panki-Bhaupur - 3rd line (11.38 km)PB/192005-2006EBRIF₹0₹30,000₹1,24,499
15Mughalsarai - Allahabad - 3rd line (150 km)PB/242015-2016CAP₹1,00,000₹2,64,82,184₹1,95,90,066
15Mughalsarai - Allahabad - 3rd line (150 km)PB/242015-2016EBRIF₹2,38,00,000₹12,216₹12,216
15Aligarh-Harduaganj flyover (22 km)PB/292016-2017CAP₹72,84,450₹1,15,02,700₹40,04,631
15Aligarh-Harduaganj flyover (22 km)PB/292016-2017EBRIF₹72,84,450₹2,90,000₹0
15Iradatganj - Kunwadih - Construction of flyover (20.1 km)PB/312016-2017CAP₹91,94,750₹1,81,04,900₹1,508
15Iradatganj - Kunwadih - Construction of flyover (20.1 km)PB/312016-2017EBRIF₹91,94,750₹91,94,800₹0
15Jeonathpur - flyover (13 km)PB/302016-2017CAP₹36,94,950₹36,94,950₹4
15Jeonathpur - flyover (13 km)PB/302016-2017EBRIF₹36,94,950₹49,66,241₹0
15Karchana-Iradatganj - Construction of flyoverPB/282016-2017CAP₹28,15,550₹19,65,970₹19,281
15Karchana-Iradatganj - Construction of flyoverPB/282016-2017EBRIF₹28,15,550₹19,65,969₹0
15Karchana-Iradatganj - Construction of flyoverPB/282016-2017EBRS₹40,000₹40,000₹-68
15Naini - Iradatganj - Construction of flyover (12 km)PB/262016-2017CAP₹33,79,750₹22,60,020₹3,154
15Naini - Iradatganj - Construction of flyover (12 km)PB/262016-2017EBRIF₹33,79,750₹22,60,020₹0
15Naini - Iradatganj - Construction of flyover (12 km)PB/262016-2017EBRS₹18₹18₹0
15Bhaupur-Panki - 4th line connecting down loop of Baupur to shunting neck of Panki (11 km)PB/342017-2018CAP₹8,18,900₹2,60,000₹4,67,080
15Bhaupur-Panki - 4th line connecting down loop of Baupur to shunting neck of Panki (11 km)PB/342017-2018EBRIF₹0₹7,13,332₹7,38,867
15Naini-Chheoki - 3rd down line with addl platform (2 km)PB/352017-2018CAP₹2,26,564₹1,53,378₹1,18,686
15Naini-Chheoki - 3rd down line with addl platform (2 km)PB/352017-2018EBRIF₹0₹3,06,251₹3,06,214
15Aligarh-Daud Khan - 3rd line (6.9 km) & construction of flyover at Daud KhanPB/452018-2019CAP₹44,79,900₹44,09,900₹38,63,535
15Aligarh-Daud Khan - 3rd line (6.9 km) & construction of flyover at Daud KhanPB/452018-2019EBRIF₹10,000₹70,000₹21,652
15Aligarh-Daud Khan - 3rd line (6.9 km) & construction of flyover at Daud KhanPB/452018-2019EBRS₹30,000₹0₹0
15Allahabad-Bamhrauli - 4th line (10 km) with fly-over at SubedarganjPB/382018-2019CAP₹49,31,100₹49,31,100₹42,60,990
15Allahabad-Bamhrauli - 4th line (10 km) with fly-over at SubedarganjPB/382018-2019EBRIF₹10,000₹10,000₹0
15Chipiyana Buzurg-Dadri - 4th line (12 km)PB/442018-2019CAP₹12,86,800₹14,20,000₹15,32,035
15Chipiyana Buzurg-Dadri - 4th line (12 km)PB/442018-2019EBRIF₹10,000₹2,39,900₹1,84,448
15Rooma-Chakeri-Chandari - 3rd line (12.5 km)PB/432018-2019CAP₹17,66,800₹9,30,000₹15,46,658
15Rooma-Chakeri-Chandari - 3rd line (12.5 km)PB/432018-2019EBRIF₹10,000₹2,90,000₹2,89,334
15Rooma-Chakeri-Chandari - 3rd line (12.5 km)PB/432018-2019EBRS₹30,000₹6,00,422₹0
15Kanpur New Coaching Complex-Kanpur (2.5 km)PB/352018-2019CAP₹3,42,800₹3,28,850₹3,23,532
15Kanpur New Coaching Complex-Kanpur (2.5 km)PB/352018-2019EBRIF₹10,000₹23,950₹23,949
15Tundla-Yamuma bridge (21 km)PB/161995-1996CAP₹2,36,000₹7,43,145₹5,98,107
15Tundla-Yamuma bridge (21 km)PB/161995-1996DPO1₹0₹33,000₹0
15Tundla-Yamuma bridge (21 km)PB/161995-1996DRF₹10,000₹3,025₹0
15Tundla-Yamuma bridge (21 km)PB/161995-1996EBRIF₹0₹1,90,000₹1,88,176
16Allahabad Division - Longer loops (10 stations)PB/572013-2014DF3₹4,04,200₹4,52,500₹3,96,696
Page 1 of 42 · 2,075 rows

Detailed table — WORK WISE

1281 projects · project ID, plan head, progress and remark link

Project IDPlan HeadShort name of workBlock section / stationPhysical %Remark link
06.02.11.97.1.30.00111Etawah-Mainpuri (57.5 km)SEC:ETW-MNQ Stn: ETW
100%
remarks/update
06.00.15.17.1.30.00115Allahabad Division - Construction of Kanpur Fly-overSEC:CNB-BZM Stn: CNB
0%
remarks/update
06.00.15.22.1.38.00115Pankidhan-GMC (2 km) 4th line (PB#72/NR/2022-23)SEC:PNK-CNB Stn: PNK
80%
remarks/update
06.02.15.03.1.83.00115Aligarh-Ghaziabad - 3rd line (106.15)SEC:ALJ-GZB Stn: ALJ
100%
remarks/update
06.02.15.05.1.30.00215Panki-Bhaupur - 3rd line (11.38 km)SEC:PNK-BPU Stn: PNK
100%
remarks/update
06.02.15.15.1.30.00115Mughalsarai - Allahabad - 3rd line (150 km)SEC:PRYJ-DDU Stn: PRYJ
73%
remarks/update
06.02.15.16.1.30.00115Aligarh-Harduaganj flyover (22 km)SEC:ALJN-HGJ Stn: ALJN
36%
remarks/update
06.02.15.16.1.30.00215Iradatganj - Kunwadih - Construction of flyover (20.1 km)SEC:IDGJ-JI Stn: IDGJ
0%
remarks/update
06.02.15.16.1.30.00315Jeonathpur - flyover (13 km)SEC:JEP-ALD Stn: JEP
0%
remarks/update
06.02.15.16.1.30.00415Karchana-Iradatganj - Construction of flyoverSEC:NYN-IDGJ Stn: NYN
0%
remarks/update
06.02.15.16.1.30.00515Naini - Iradatganj - Construction of flyover (12 km)SEC:NYN-IDGJ Stn: NYN
0%
remarks/update
06.02.15.17.1.30.00115Bhaupur-Panki - 4th line connecting down loop of Baupur to shunting neck of Panki (11 km)SEC:PNK-BPU Stn: PNK
100%
remarks/update
06.02.15.17.1.30.00215Naini-Chheoki - 3rd down line with addl platform (2 km)SEC:COI-ALD Stn: COI
100%
remarks/update
06.02.15.18.1.30.00115Aligarh-Daud Khan - 3rd line (6.9 km) & construction of flyover at Daud KhanSEC:ALJN-DAQ Stn: ALJN
83%
remarks/update
06.02.15.18.1.30.00215Allahabad-Bamhrauli - 4th line (10 km) with fly-over at SubedarganjSEC:ALD-BMU Stn: ALD
90%
remarks/update
06.02.15.18.1.30.00315Chipiyana Buzurg-Dadri - 4th line (12 km)SEC:MIU-DER Stn: MIU
90%
remarks/update
06.02.15.18.1.30.00515Rooma-Chakeri-Chandari - 3rd line (12.5 km)SEC:RXM-CNBI Stn: RXM
100%
remarks/update
06.02.15.18.1.51.00415Kanpur New Coaching Complex-Kanpur (2.5 km)SEC: Stn: CNB
90%
remarks/update
06.02.15.95.1.30.00215Tundla-Yamuma bridge (21 km)SEC:TDL -JAB Stn: TDL
100%
remarks/update
06.00.16.13.1.30.00416Allahabad Division - Longer loops (10 stations)SEC:TDL-ALD Stn: TDL
98%
remarks/update
06.02.16.02.1.30.00116Aligarh Jn - Shifting of goods shed to CD siding alongwith second block rake siding & development of passenger & parcel complex on city sideSEC: Stn: ALJN
100%
remarks/update
06.02.16.05.1.30.00216Etmadpur-Mitawali - Link line bypassing TundlaSEC:ETUE-MTI Stn: ETUE
100%
remarks/update
06.02.16.05.1.30.00316Govindpur - Addl. loopsSEC:CNB-ETW Stn: CNB
100%
remarks/update
06.02.16.08.1.16.00116Aligarh-Ghaziabad - Automatic signalling in place of absolute block working on up line in connection with 3rd lineSEC:ALJN-GZB Stn: ALJN
99%
remarks/update
06.02.16.08.1.16.00216Aligarh-Ghaziabad - Bidirectional automatic signalling on middle line in connection with 3rd lineSEC:ALJN-GZB Stn: ALJN
99%
remarks/update
06.02.16.10.1.30.00116Aligarh Jn - Improvement of station with provision of one down loop & one platformSEC: Stn: ALJN
100%
remarks/update
06.02.16.10.1.30.00216Unchdih - Directional loop in place of common loop with new station buildingSEC: Stn: UND
99%
remarks/update
06.02.16.11.1.51.00216Mughalsarai-Aligarh - Extension of short loops (18 Nos)SEC:MGS-GZB Stn: MGS
99%
remarks/update
06.02.16.16.2.51.00116Kanpur central-Kanpur: Improvement of damaged drain/Nala in CPC goods shed kanpur.SEC: Stn: CNB
99%
remarks/update
06.02.16.18.3.30.00216Allahabad Division - Development of Subedarganj station as satelite Station.SEC: Stn: SFG
99%
remarks/update
06.02.16.18.3.30.00416Allahabad Division- Conversion of 'D' class station (Vishwanathpuri) into ‘B’ class station between Chunar and Shakteshgarh.(20.94 Km)SEC:CAR-SKGH Stn: CAR
99%
remarks/update
06.02.16.18.3.51.00116Kanpur Central - Provision of simultaneous movement from 3rd & 4th line at Ghaziabad end and from North & south lines at Lucknow end.SEC: Stn: CNB
80%
remarks/update
06.02.16.18.3.51.00316Allahabad Division.Provision of 20 Sand Humps/Over runs between Allahabad-Kanpur Section.SEC:CNB-ALD Stn: CNB
99%
remarks/update
06.02.16.19.3.51.00316Allahabad Division -Provision of rest room at 33 way side Stations and attached toilets at 48 road side stations.SEC:MGS-GZB Stn: MGS
55%
remarks/update
06.02.16.19.3.51.00416Two small spurs at Kanpur Anwarganj station may be extended and PF be made on second line.SEC: Stn: CPA
10%
remarks/update
06.02.16.19.3.51.00616Development & Modernization of Control office of Allahabad including HQ control office on the line of East Coast Railway.SEC: Stn: ALD
80%
remarks/update
06.02.16.19.3.51.00716Extension of line No. 08 at Mirzapur for loading and unloading on high level platform and extension of shunting neck to full length.SEC: Stn: MZP
90%
remarks/update
06.02.16.20.3.51.00316Chunar- Converting line no 14 into additional DD line and Improvement of P.F. Surface of goods shed area by released PSC sleeperSEC: Stn: CAR
88%
remarks/update
06.02.16.20.3.51.00516Prayagraj Division - Raising and Improvement of Shikohabad goods shed.SEC: Stn: SKB
87%
remarks/update
06.02.16.21.1.51.00116Prayagraj Division - Raising and Improvement of 03 Goods sheds of Prayagraj Division. (ETW, ETH, HRF).SEC:MGS-GZB Stn: MGS
90%
remarks/update
06.02.16.21.1.51.00216Prayagraj Division - Raising of speed in Chunar - Chopan section.SEC:CAR-CPU Stn: CAR
65%
remarks/update
06.02.16.21.3.38.01116Prayagraj Division - Electrification of cross overs, Hot axle, Goods Wharf and other sidings of stations GMC area.SEC:MGS-ALD Stn: MGS
95%
remarks/update
06.02.16.21.3.51.00116Prayagraj Division - Extension of road surface area of Sonbhadra goods shed and wharf area of Shakteshgarh goods shed.SEC: Stn: SKGH
95%
remarks/update
06.02.16.21.3.51.00416Prayagraj Division - Connectivity of CPC siding to Shunting neck of CPA station.SEC: Stn: CPA
50%
remarks/update
06.02.16.21.3.51.00716Prayagraj Division - Electrification of Cross overs Hot axle, Goods Wharf and other sidings of stations between PRYJ-CNB.SEC:ALD-CNB Stn: ALD
85%
remarks/update
06.02.16.21.3.51.00816Prayagraj Division -Provision of common rest room for male and female at 23 way side Stations for facilitating train operations.SEC:MGS-GZB Stn: MGS
98%
remarks/update
06.02.16.21.3.51.00916Electrification of Cross overs, Hot axle, Goods Wharf and other sidings of stations between DDU-PRYJ in PRYJ Division.SEC:MGS-ALD Stn: MGS
85%
remarks/update
06.02.16.21.3.51.01016Prayagraj Division - Electrification of Cross overs, Hot axle, Goods Wharf and other sidings of stations between PNKD-TDL.SEC:PNK-TDL Stn: PNK
95%
remarks/update
06.02.16.21.3.51.01216Prayagraj Division - Electrification of Cross overs, Hot axle, Goods Wharf and other sidings of stations between TDL-GZB & CPA station.SEC:TDL-GZB Stn: TDL
85%
remarks/update
06.02.16.22.1.38.00116PRYJ-ALJN section - Provision of 18 Overrun/Sand Hump in 12 stations of Prayagraj Division Phase-II as safety overlap for simultaneous reception.SEC:CNB-ALJN Stn: CNB
15%
remarks/update
Page 1 of 26 · 1,281 rows