North Central Railway

Prayagraj Division · IRPSM Work Intelligence

6
DR

Sanctioned works

Remarks

Every remark recorded against a sanctioned work, preserved historically alongside the IRPSM remark imported from the statement.

Filters

Found 1 remark records

Remarks register

Showing 1 to 1 of 1

Rows
SNProject nameExecuting agencySac. yearCostIRPSM remarksRemarks 1
1Bhaupur-Panki - 4th line connecting down loop of Baupur to shunting neck of Panki (11 km)CAO(CON)/NCR2017-2018₹9,73,332Project commissioned for passenger traffic after CRS inspection on 20.04.2022. Final bill for EW in formation & major +minor bridges passed in April-23. Final bill of linking work passed in March-24. Completion report will be drawn after passing of final bills of S&T and Electrical. Letter issued to Dy.CSTE/C/PRYJ & Dy.CEE/C/CNB on 19.12.24 ask for final expenditure. Last reminder issued on 20.11.25 to Dy.CSTE/C/PRYJ.
Page 1 of 1