North Central Railway

Prayagraj Division · IRPSM Work Intelligence

6
DR

Oversight

DRM Review

DRM reviews works at any stage before sanction. Reviews are an oversight layer — they never replace department processing, and each review is stored as a new historical record.

Works under oversight

24

Reviews recorded

11

Open directions

10

Not reviewed yet

17

Works awaiting / under DRM oversight

Position, stage and last review

Work IDWork NameStageDays at stageDepartments completedLast DRM remark
WORK-2026-0001Foot over bridge with lift at KhagaIdea34Not reviewed yet
WORK-2026-0002Provision of second entry at Prayagraj RambagIdea36Not reviewed yet
WORK-2026-0003Extension of platform no. 3 at FatehpurIdea24Not reviewed yet
WORK-2026-0004Washable apron on platform 1 at FatehpurJoint Inspection183 / 422 Feb 2026 — Progress reviewed. Department input from Electrical is still awaited.
WORK-2026-0005Yard remodelling for loop line at Naini JunctionJoint Inspection153 / 4Not reviewed yet
WORK-2026-0006Complete track renewal near SirathuJoint Inspection251 / 2Not reviewed yet
WORK-2026-0007Electronic interlocking renewal at FatehpurJoint Inspection451 / 215 Feb 2026 — Directed to expedite the survey and place report in next review.
WORK-2026-0008Air-conditioned waiting hall at Naini JunctionSurvey63 / 3Not reviewed yet
WORK-2026-0009Road over bridge in lieu of LC-14 near Chitrakoot DhamSurvey313 / 3Not reviewed yet
WORK-2026-0010Escalator provision at Prayagraj RambagSurvey332 / 207 Feb 2026 — Cost revision noted; justification to be recorded on file.
WORK-2026-0011Augmentation of water supply at SubedarganjFeasibility332 / 2Not reviewed yet
WORK-2026-0012Type-II staff quarters at Chitrakoot DhamFeasibility184 / 4Not reviewed yet
WORK-2026-0013Foot over bridge with lift at Prayagraj JunctionFeasibility192 / 213 Mar 2026 — Cost revision noted; justification to be recorded on file.
WORK-2026-0014Provision of second entry at Prayagraj JunctionCost Assessment264 / 4Not reviewed yet
WORK-2026-0015Extension of platform no. 3 at Chitrakoot DhamCost Assessment34 / 4Not reviewed yet
WORK-2026-0016Washable apron on platform 1 at KhagaWork Created434 / 428 Jan 2026 — Progress reviewed. Department input from Electrical is still awaited.
WORK-2026-0017Yard remodelling for loop line at JhunsiWork Created72 / 2Not reviewed yet
WORK-2026-0018Complete track renewal near Chheoki JunctionWork Created402 / 2Not reviewed yet
WORK-2026-0019Electronic interlocking renewal at ShankargarhShortlisted443 / 316 Feb 2026 — Cost revision noted; justification to be recorded on file.
WORK-2026-0020Air-conditioned waiting hall at Manikpur JunctionShortlisted102 / 2Not reviewed yet
WORK-2026-0021Road over bridge in lieu of LC-14 near Manikpur JunctionUnder Approval334 / 4Not reviewed yet
WORK-2026-0022Escalator provision at Meja RoadUnder Approval194 / 421 Feb 2026 — Field position explained by Sr. DEN. Work considered necessary.
WORK-2026-0023Augmentation of water supply at SirathuUnder Approval303 / 3Not reviewed yet
WORK-2026-0024Type-II staff quarters at SubedarganjUnder Approval62 / 2Not reviewed yet

DRM follow-up actions

Directions issued to departments

WORK-2026-0004OperatingSubmit pending department input with observation and cost.Due 15 Apr 2026Overdue
WORK-2026-0007ElectricalSubmit pending department input with observation and cost.Due 03 May 2026Pending
WORK-2026-0010MechanicalSubmit pending department input with observation and cost.Due 03 May 2026Pending
WORK-2026-0010MechanicalSubmit pending department input with observation and cost.Due 15 Apr 2026Overdue
WORK-2026-0013EngineeringSubmit pending department input with observation and cost.Due 03 May 2026Pending
WORK-2026-0016CommercialSubmit pending department input with observation and cost.Due 03 May 2026Pending
WORK-2026-0016CommercialSubmit pending department input with observation and cost.Due 15 Apr 2026Overdue
WORK-2026-0019S&TSubmit pending department input with observation and cost.Due 03 May 2026Pending
WORK-2026-0022EngineeringSubmit pending department input with observation and cost.Due 03 May 2026Pending
WORK-2026-0022EngineeringSubmit pending department input with observation and cost.Due 15 Apr 2026Overdue