Stage 02
Joint Inspection
Departments are selected from master data and work in parallel. Each department keeps its own responsibility record — consolidation never overwrites it.
Assign a joint inspection
Works under joint inspection
Consolidated departmental progress
Finance
CompletedSr. DFM • due 02 Jan 2026
Finance inspected the site; the proposal is technically workable with minor modification at the approach side.
Engineering
CompletedSr. DEN (Co-ord) • due 02 Jan 2026
Engineering inspected the site; the proposal is technically workable with minor modification at the approach side.
Mechanical
CompletedSr. DME • due 02 Jan 2026
Mechanical inspected the site; the proposal is technically workable with minor modification at the approach side.
Operating
In ProgressSr. DOM • due 02 Jan 2026
Engineering
CompletedSr. DEN (Co-ord) • due 03 Jan 2026
Engineering inspected the site; the proposal is technically workable with minor modification at the approach side.
Electrical
CompletedSr. DEE (TRD) • due 03 Jan 2026
Electrical inspected the site; the proposal is technically workable with minor modification at the approach side.
Mechanical
CompletedSr. DME • due 03 Jan 2026
Mechanical inspected the site; the proposal is technically workable with minor modification at the approach side.
S&T
Clarification RequiredSr. DSTE • due 03 Jan 2026
S&T
CompletedSr. DSTE • due 06 Mar 2026
S&T inspected the site; the proposal is technically workable with minor modification at the approach side.
Mechanical
In ProgressSr. DME • due 06 Mar 2026
Commercial
CompletedSr. DCM • due 02 Jan 2026
Commercial inspected the site; the proposal is technically workable with minor modification at the approach side.
Electrical
PendingSr. DEE (TRD) • due 02 Jan 2026
Engineering
CompletedSr. DEN (Co-ord) • due 27 Oct 2025
Engineering inspected the site; the proposal is technically workable with minor modification at the approach side.
S&T
CompletedSr. DSTE • due 27 Oct 2025
S&T inspected the site; the proposal is technically workable with minor modification at the approach side.
Finance
CompletedSr. DFM • due 27 Oct 2025
Finance inspected the site; the proposal is technically workable with minor modification at the approach side.
Operating
CompletedSr. DOM • due 16 Jan 2026
Operating inspected the site; the proposal is technically workable with minor modification at the approach side.
S&T
CompletedSr. DSTE • due 16 Jan 2026
S&T inspected the site; the proposal is technically workable with minor modification at the approach side.
Engineering
CompletedSr. DEN (Co-ord) • due 16 Jan 2026
Engineering inspected the site; the proposal is technically workable with minor modification at the approach side.
S&T
CompletedSr. DSTE • due 28 Feb 2026
S&T inspected the site; the proposal is technically workable with minor modification at the approach side.
Mechanical
CompletedSr. DME • due 28 Feb 2026
Mechanical inspected the site; the proposal is technically workable with minor modification at the approach side.
Mechanical
CompletedSr. DME • due 30 Dec 2025
Mechanical inspected the site; the proposal is technically workable with minor modification at the approach side.
S&T
CompletedSr. DSTE • due 30 Dec 2025
S&T inspected the site; the proposal is technically workable with minor modification at the approach side.
Operating
CompletedSr. DOM • due 16 Feb 2026
Operating inspected the site; the proposal is technically workable with minor modification at the approach side.
Electrical
CompletedSr. DEE (TRD) • due 16 Feb 2026
Electrical inspected the site; the proposal is technically workable with minor modification at the approach side.
Finance
CompletedSr. DFM • due 16 Feb 2026
Finance inspected the site; the proposal is technically workable with minor modification at the approach side.
S&T
CompletedSr. DSTE • due 16 Feb 2026
S&T inspected the site; the proposal is technically workable with minor modification at the approach side.
Finance
CompletedSr. DFM • due 13 Feb 2026
Finance inspected the site; the proposal is technically workable with minor modification at the approach side.
Engineering
CompletedSr. DEN (Co-ord) • due 13 Feb 2026
Engineering inspected the site; the proposal is technically workable with minor modification at the approach side.
S&T
CompletedSr. DSTE • due 06 Jan 2026
S&T inspected the site; the proposal is technically workable with minor modification at the approach side.
Mechanical
CompletedSr. DME • due 06 Jan 2026
Mechanical inspected the site; the proposal is technically workable with minor modification at the approach side.
Commercial
CompletedSr. DCM • due 06 Jan 2026
Commercial inspected the site; the proposal is technically workable with minor modification at the approach side.
Engineering
CompletedSr. DEN (Co-ord) • due 06 Jan 2026
Engineering inspected the site; the proposal is technically workable with minor modification at the approach side.
S&T
CompletedSr. DSTE • due 22 Sept 2025
S&T inspected the site; the proposal is technically workable with minor modification at the approach side.
Commercial
CompletedSr. DCM • due 22 Sept 2025
Commercial inspected the site; the proposal is technically workable with minor modification at the approach side.
Operating
CompletedSr. DOM • due 22 Sept 2025
Operating inspected the site; the proposal is technically workable with minor modification at the approach side.
Electrical
CompletedSr. DEE (TRD) • due 22 Sept 2025
Electrical inspected the site; the proposal is technically workable with minor modification at the approach side.
Mechanical
CompletedSr. DME • due 17 Sept 2025
Mechanical inspected the site; the proposal is technically workable with minor modification at the approach side.
Electrical
CompletedSr. DEE (TRD) • due 17 Sept 2025
Electrical inspected the site; the proposal is technically workable with minor modification at the approach side.
Finance
CompletedSr. DFM • due 17 Sept 2025
Finance inspected the site; the proposal is technically workable with minor modification at the approach side.
Commercial
CompletedSr. DCM • due 17 Sept 2025
Commercial inspected the site; the proposal is technically workable with minor modification at the approach side.
Finance
CompletedSr. DFM • due 21 Apr 2026
Finance inspected the site; the proposal is technically workable with minor modification at the approach side.
Electrical
CompletedSr. DEE (TRD) • due 21 Apr 2026
Electrical inspected the site; the proposal is technically workable with minor modification at the approach side.
Electrical
CompletedSr. DEE (TRD) • due 18 Apr 2026
Electrical inspected the site; the proposal is technically workable with minor modification at the approach side.
Engineering
CompletedSr. DEN (Co-ord) • due 18 Apr 2026
Engineering inspected the site; the proposal is technically workable with minor modification at the approach side.
Engineering
CompletedSr. DEN (Co-ord) • due 04 Apr 2026
Engineering inspected the site; the proposal is technically workable with minor modification at the approach side.
Mechanical
CompletedSr. DME • due 04 Apr 2026
Mechanical inspected the site; the proposal is technically workable with minor modification at the approach side.
S&T
CompletedSr. DSTE • due 04 Apr 2026
S&T inspected the site; the proposal is technically workable with minor modification at the approach side.
Operating
CompletedSr. DOM • due 24 Jan 2026
Operating inspected the site; the proposal is technically workable with minor modification at the approach side.
Engineering
CompletedSr. DEN (Co-ord) • due 24 Jan 2026
Engineering inspected the site; the proposal is technically workable with minor modification at the approach side.
S&T
CompletedSr. DSTE • due 10 Oct 2025
S&T inspected the site; the proposal is technically workable with minor modification at the approach side.
Mechanical
CompletedSr. DME • due 10 Oct 2025
Mechanical inspected the site; the proposal is technically workable with minor modification at the approach side.
Engineering
CompletedSr. DEN (Co-ord) • due 10 Oct 2025
Engineering inspected the site; the proposal is technically workable with minor modification at the approach side.
Operating
CompletedSr. DOM • due 10 Oct 2025
Operating inspected the site; the proposal is technically workable with minor modification at the approach side.
Electrical
CompletedSr. DEE (TRD) • due 13 Mar 2026
Electrical inspected the site; the proposal is technically workable with minor modification at the approach side.
Operating
CompletedSr. DOM • due 13 Mar 2026
Operating inspected the site; the proposal is technically workable with minor modification at the approach side.
Finance
CompletedSr. DFM • due 13 Mar 2026
Finance inspected the site; the proposal is technically workable with minor modification at the approach side.
Engineering
CompletedSr. DEN (Co-ord) • due 13 Mar 2026
Engineering inspected the site; the proposal is technically workable with minor modification at the approach side.
Mechanical
CompletedSr. DME • due 14 Dec 2025
Mechanical inspected the site; the proposal is technically workable with minor modification at the approach side.
Electrical
CompletedSr. DEE (TRD) • due 14 Dec 2025
Electrical inspected the site; the proposal is technically workable with minor modification at the approach side.
S&T
CompletedSr. DSTE • due 14 Dec 2025
S&T inspected the site; the proposal is technically workable with minor modification at the approach side.
Engineering
CompletedSr. DEN (Co-ord) • due 14 Oct 2025
Engineering inspected the site; the proposal is technically workable with minor modification at the approach side.
Operating
CompletedSr. DOM • due 14 Oct 2025
Operating inspected the site; the proposal is technically workable with minor modification at the approach side.