North Central Railway

Prayagraj Division · IRPSM Work Intelligence

6
DR

Stage 04

Feasibility

Department-wise technical and operational examination recorded before cost assessment.

Augmentation of water supply at Subedarganj

WORK-2026-0011 • 2 department observation(s)

Department

Mechanical

Date

12 Feb 2026

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Department

S&T

Date

12 Feb 2026

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Type-II staff quarters at Chitrakoot Dham

WORK-2026-0012 • 2 department observation(s)

Department

Operating

Date

01 Apr 2026

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Department

Electrical

Date

01 Apr 2026

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Foot over bridge with lift at Prayagraj Junction

WORK-2026-0013 • 2 department observation(s)

Department

Finance

Date

29 Mar 2026

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Department

Engineering

Date

29 Mar 2026

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Provision of second entry at Prayagraj Junction

WORK-2026-0014 • 2 department observation(s)

Department

S&T

Date

19 Feb 2026

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Department

Mechanical

Date

19 Feb 2026

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Extension of platform no. 3 at Chitrakoot Dham

WORK-2026-0015 • 2 department observation(s)

Department

S&T

Date

05 Nov 2025

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Department

Commercial

Date

05 Nov 2025

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Washable apron on platform 1 at Khaga

WORK-2026-0016 • 2 department observation(s)

Department

Mechanical

Date

31 Oct 2025

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Department

Electrical

Date

31 Oct 2025

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Yard remodelling for loop line at Jhunsi

WORK-2026-0017 • 2 department observation(s)

Department

Finance

Date

15 Apr 2026

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Department

Electrical

Date

15 Apr 2026

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Complete track renewal near Chheoki Junction

WORK-2026-0018 • 2 department observation(s)

Department

Electrical

Date

15 Apr 2026

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Department

Engineering

Date

15 Apr 2026

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Electronic interlocking renewal at Shankargarh

WORK-2026-0019 • 2 department observation(s)

Department

Engineering

Date

15 Apr 2026

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Department

Mechanical

Date

15 Apr 2026

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Air-conditioned waiting hall at Manikpur Junction

WORK-2026-0020 • 2 department observation(s)

Department

Operating

Date

09 Mar 2026

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Department

Engineering

Date

09 Mar 2026

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Road over bridge in lieu of LC-14 near Manikpur Junction

WORK-2026-0021 • 2 department observation(s)

Department

S&T

Date

23 Nov 2025

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Department

Mechanical

Date

23 Nov 2025

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Escalator provision at Meja Road

WORK-2026-0022 • 2 department observation(s)

Department

Electrical

Date

15 Apr 2026

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Department

Operating

Date

15 Apr 2026

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Augmentation of water supply at Sirathu

WORK-2026-0023 • 2 department observation(s)

Department

Mechanical

Date

27 Jan 2026

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Department

Electrical

Date

27 Jan 2026

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Type-II staff quarters at Subedarganj

WORK-2026-0024 • 2 department observation(s)

Department

Engineering

Date

27 Nov 2025

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.

Department

Operating

Date

27 Nov 2025

Recommendation

Recommended for inclusion in works programme.

Technical

Technically feasible with standard drawings; no deviation from schedule of dimensions.

Operational

Can be executed with traffic blocks of 3 hours on alternate days.

Constraints / Risks

Limited working space on platform side during peak hours. · Monsoon may delay foundation work by 3-4 weeks.