Stage 05
Cost Assessment
Every revision is stored as a new record showing previous cost, revised cost, difference and reason.
Record a cost / revision
Cost history
All revisions preserved
| Work ID | Rev | Date | Department | Previous | Revised | Difference | Reason |
|---|---|---|---|---|---|---|---|
| WORK-2026-0014 | 1 | 13 Mar 2026 | S&T | — | ₹21.32 Cr | — | Initial abstract estimate prepared on the basis of survey findings. |
| WORK-2026-0015 | 1 | 27 Nov 2025 | S&T | — | ₹1.45 Cr | — | Initial abstract estimate prepared on the basis of survey findings. |
| WORK-2026-0016 | 1 | 22 Nov 2025 | Mechanical | — | ₹3.61 Cr | — | Initial abstract estimate prepared on the basis of survey findings. |
| WORK-2026-0017 | 1 | 18 Apr 2026 | Finance | — | ₹2.74 Cr | — | Initial abstract estimate prepared on the basis of survey findings. |
| WORK-2026-0017 | 2 | 18 Apr 2026 | Finance | ₹2.74 Cr | ₹2.96 Cr | ₹0.22 Cr | Scope enhanced on DRM direction during works review. |
| WORK-2026-0017 | 3 | 18 Apr 2026 | Finance | ₹2.96 Cr | ₹3.17 Cr | ₹0.21 Cr | Rate revision as per updated schedule of rates. |
| WORK-2026-0018 | 1 | 18 Apr 2026 | Electrical | — | ₹18.01 Cr | — | Initial abstract estimate prepared on the basis of survey findings. |
| WORK-2026-0018 | 2 | 18 Apr 2026 | Electrical | ₹18.01 Cr | ₹19.43 Cr | ₹1.42 Cr | Scope enhanced on DRM direction during works review. |
| WORK-2026-0019 | 1 | 18 Apr 2026 | Engineering | — | ₹8.25 Cr | — | Initial abstract estimate prepared on the basis of survey findings. |
| WORK-2026-0020 | 1 | 31 Mar 2026 | Operating | — | ₹6.43 Cr | — | Initial abstract estimate prepared on the basis of survey findings. |
| WORK-2026-0021 | 1 | 15 Dec 2025 | S&T | — | ₹13.47 Cr | — | Initial abstract estimate prepared on the basis of survey findings. |
| WORK-2026-0021 | 2 | 27 Dec 2025 | S&T | ₹13.47 Cr | ₹14.53 Cr | ₹1.06 Cr | Revised after inclusion of utility shifting and approach work. |
| WORK-2026-0022 | 1 | 18 Apr 2026 | Electrical | — | ₹20.24 Cr | — | Initial abstract estimate prepared on the basis of survey findings. |
| WORK-2026-0023 | 1 | 18 Feb 2026 | Mechanical | — | ₹16.78 Cr | — | Initial abstract estimate prepared on the basis of survey findings. |
| WORK-2026-0024 | 1 | 19 Dec 2025 | Engineering | — | ₹5.57 Cr | — | Initial abstract estimate prepared on the basis of survey findings. |
| WORK-2026-0024 | 2 | 31 Dec 2025 | Engineering | ₹5.57 Cr | ₹6.01 Cr | ₹0.44 Cr | Rate revision as per updated schedule of rates. |
| WORK-2026-0024 | 3 | 12 Jan 2026 | Engineering | ₹6.01 Cr | ₹6.45 Cr | ₹0.44 Cr | Scope enhanced on DRM direction during works review. |