North Central Railway

Prayagraj Division · IRPSM Work Intelligence

6
DR
WORK-2026-0007Sample data

Electronic interlocking renewal at Fatehpur

Joint InspectionNOT SANCTIONEDNormal priorityPrayagraj–FatehpurFatehpurCommercial, Electrical

Latest estimated cost

₹12.05 Cr

45 days at current stage

Work particulars

Originated By

Public Representation

Originating Department

Commercial

Created On

07 Dec 2025

Source of Proposal

Passenger Representation

Zone

North Central Railway (NCR)

Division

Prayagraj Division

Section

Prayagraj–Fatehpur

Station

Fatehpur

District

Fatehpur

Location

Km 643/8 near Fatehpur

Plan Head

PH-11 Passenger Amenities

Work Category

Signalling

Work Type

Signal Renewal

Executing Agency

Electrical Project Unit

Year

2024-25

Shortlisting

Pending

Problem / Requirement

Existing asset has outlived codal life and needs replacement.

Justification

Supports projected traffic growth on the section.

Description

Electronic interlocking renewal at Fatehpur in Prayagraj–Fatehpur section of Prayagraj Division to address persistent operational and passenger requirements reported by the field units.