WORK-2026-0003Sample data
Extension of platform no. 3 at Fatehpur
IdeaNOT SANCTIONEDHigh priorityPrayagraj–Fatehpur • Fatehpur • Finance, Engineering, Commercial
Latest estimated cost
₹12.88 Cr
24 days at current stage
Work particulars
Originated By
Sr. DEN (Co-ord)
Originating Department
Finance
Created On
25 Feb 2026
Source of Proposal
DRM Inspection
Zone
North Central Railway (NCR)
Division
Prayagraj Division
Section
Prayagraj–Fatehpur
Station
Fatehpur
District
Fatehpur
Location
Km 659/0 near Fatehpur
Plan Head
PH-33 Electrification Projects
Work Category
Capacity Enhancement
Work Type
Platform Extension
Executing Agency
RVNL
Year
2025-26
Shortlisting
Pending
Problem / Requirement
Severe passenger congestion during peak hours and festival rush.
Justification
Essential passenger amenity as per divisional amenity norms.
Description
Extension of platform no. 3 at Fatehpur in Prayagraj–Fatehpur section of Prayagraj Division to address persistent operational and passenger requirements reported by the field units.