North Central Railway

Prayagraj Division · IRPSM Work Intelligence

6
DR

Sanctioned works

Remarks

Every remark recorded against a sanctioned work, preserved historically alongside the IRPSM remark imported from the statement.

Filters

Found 1 remark records

Remarks register

Showing 1 to 1 of 1

Rows
SNProject nameExecuting agencySac. yearCostIRPSM remarksRemarks 1
1Chipiyana Buzurg-Dadri - 4th line (12 km)CAO(CON)/NCR2018-2019₹16,59,900• 4th line between Chipiyana Buzurg– Dadri has been opened for Goods traffic after CRS inspection on 25.03.2023 and 22.06.2023 for DER-MIU and MIU-CPYZ section respectively._x000D_ • Further for opening of section for passenger traffic, connectivity of 4th line in Dadri yard is involved for which NTPC land is required. NTPC vide their letter dt 14.09.2023 has agreed to give their land of 5334 Sqm. Payment of Rs 4.14 Crore has been released to NTPC but transfer of land is still pending. _x000D_ DER NI IS PLA
Page 1 of 1