SNProject nameExecuting agencySac. yearCostIRPSM remarksRemarks 1
1Extension of line No. 08 at Mirzapur for loading and unloading on high level platform and extension of shunting neck to full length.DRM/ALD2019-2020₹21,602Engg: Shunting neck work completed. Wharf surfacing with inverted sleepers under progress 80%. 100 sleepers balance to be laid. Merchant & labour room completed. Other related work is in progress. _x000D_ TRD:-TRD work completed (P-100%, F-0% TRD share not included). _x000D_ _x000D_ _x000D_