SNProject nameExecuting agencySac. yearCostIRPSM remarksRemarks 1
1Chunar- Converting line no 14 into additional DD line and Improvement of P.F. Surface of goods shed area by released PSC sleeperDRM/ALD2020-2021₹24,845Engg: Dismantling of Line no - 13 completed. Sleeper laying in between line no 12 & 14 completed, 720 mtr. out of 720 mtr. done. (barrack renovation work for CGS office, Labour & Merchant room work phy. completed.),Surfacing of good shed by relesed PSC Sleepers completed, Balance 150 mtr RCC Boundary wall foundation work completed. Final variation done. _x000D_ _x000D_ ELG: One HMT to be erected. RITES call rejected the material. Fresh RITES call to be invited. Outlay - Nil TRD:- TRD share is not included