| SN | Project name | Executing agency | Sac. year | Cost | IRPSM remarks | Remarks 1 |
|---|---|---|---|---|---|---|
| 1 | Mughalsarai - Allahabad - 3rd line (150 km) | CAO(CON)/NCR | 2015-2016 | ₹2,64,94,400 | Prayagraj Cheoki to Bheerpur, Birohi to Vindhyachal & Kailhat to Block Hut K (total approx. 42 km) section commissioned. Work is in progress on major bridges , important bridge on River tons and in yards in progress. Out of 113 minor bridges 109 minor Bridge are completed and 8 in progress . | — |