Sanctioned works
Remarks
Every remark recorded against a sanctioned work, preserved historically alongside the IRPSM remark imported from the statement.
Filters
Found 1 remark records
Remarks register
Showing 1 to 1 of 1
Rows
| SN | Project name | Executing agency | Sac. year | Cost | IRPSM remarks | Remarks 1 |
|---|---|---|---|---|---|---|
| 1 | Allahabad Division - Construction of Kanpur Fly-over | CAO(CON)/NCR | 2017-2018 | ₹0 | DPR has been submitted in Railway Board on 28.06.2018. Approval awaited. Howevr, New work for Final Location Survey for Kanpur Flyover (14.47 km) has been sanctioned by Railway Board vide their letter no. 2022/W-2/Survey/Budget/1 (E-3395658) dt. 25.07.2022 & 04.08.2022 at a cost of Rs. 28.94 lacs. FLS estimate sanctioned by CAO/C/NCR on 25.04.2024. Tender for FLS work invited in 3 times but discharged. Now again tender opened on 05.02.2026 & under finalization. | — |