SNProject nameExecuting agencySac. yearCostIRPSM remarksRemarks 1
1Allahabad Division - Construction of Kanpur Fly-overCAO(CON)/NCR2017-2018₹0DPR has been submitted in Railway Board on 28.06.2018. Approval awaited. Howevr, New work for Final Location Survey for Kanpur Flyover (14.47 km) has been sanctioned by Railway Board vide their letter no. 2022/W-2/Survey/Budget/1 (E-3395658) dt. 25.07.2022 & 04.08.2022 at a cost of Rs. 28.94 lacs. FLS estimate sanctioned by CAO/C/NCR on 25.04.2024. Tender for FLS work invited in 3 times but discharged. Now again tender opened on 05.02.2026 & under finalization.