| SN | Project name | Executing agency | Sac. year | Cost | IRPSM remarks | Remarks 1 |
|---|---|---|---|---|---|---|
| 1 | Prayagraj Division - Electrification of Cross overs Hot axle, Goods Wharf and other sidings of stations between PRYJ-CNB. | DRM/ALD | 2021-2022 | ₹23,495 | Work awarded on 09.12.2022 . Survey done. Drawing approved. Material supplied. Station wise work progress:_x000D_ 1. KGA- OHE work completed.._x000D_ 2. KTCE- OHE work completed._x000D_ 3. KUW- OHE work completed._x000D_ 4. SRO- OHE work completed._x000D_ 5. RUB- OHE work completed._x000D_ 6. Ramva- OHE work completed._x000D_ 7. KKS- OHE work completed._x000D_ 8. BKO- OHE work completed._x000D_ 9. FYZ- OHE work completed._x000D_ 10. KBN- OHE work completed._x000D_ Final variation is under preparation. | — |