Sanctioned works
Remarks
Every remark recorded against a sanctioned work, preserved historically alongside the IRPSM remark imported from the statement.
Filters
Found 1 remark records
Remarks register
Showing 1 to 1 of 1
Rows
| SN | Project name | Executing agency | Sac. year | Cost | IRPSM remarks | Remarks 1 |
|---|---|---|---|---|---|---|
| 1 | Allahabad-Bamhrauli - 4th line (10 km) with fly-over at Subedarganj | CAO(CON)/NCR | 2018-2019 | ₹49,41,100 | Pile & Pilecap completed. Pier and Pier Cap work, Girder launching, deck slab work Parallelly is in progress._x000D_ Formation along with Retaining wall in progress. Minor Bridges completed. FOB in progress. | — |
Page 1 of 1