| SN | Project name | Executing agency | Sac. year | Cost | IRPSM remarks | Remarks 1 |
|---|---|---|---|---|---|---|
| 1 | Prayagraj Division - Electrification of Cross overs, Hot axle, Goods Wharf and other sidings of stations between PNKD-TDL. | DRM/ALD | 2021-2022 | ₹23,599 | Work was awarded on 12.12.2022._x000D_ Scope of work- 06 stn HNG, SKB, BDN, JGR, BNT & PHD stns covered for electrification as per LOA qty. Material supplied. _x000D_ 1. PHD- Work completed._x000D_ 2. BNT- Work completed._x000D_ 3. JGR- Work completed._x000D_ 4. SKB- Work completed._x000D_ 5. BDN- Work completed._x000D_ 6. HNG- Work completed. _x000D_ Final variation is under preparation. | — |