SNProject nameExecuting agencySac. yearCostIRPSM remarksRemarks 1
1Aligarh-Harduaganj flyover (22 km)CAO(CON)/NCR2016-2017₹1,17,92,700Work is being executed by Bridge & roof Co. India Ltd. New Delhi vide Rly. Board letter dtd 14.09.20. MOU signed on 01.02.21. Rs.50 Cr has been taken by Br.& Roof India on 24.02.22 as advance payment wrt clause7.2 of MOU against the Bank Guarantee. DE is under vetting with finance since 11.02.2025. Land acquisition is under progress.